I was at a party recently, talking with a driller from a geotechnical drilling company. I showed him the drilling cost calculator I built. It prices four methods side by side, and he stopped at the fourth one. Why is sonic even on there? Sonic is always more expensive than hollow stem auger. Everybody knows that.
Per foot, he has a point. I work mostly on Florida petroleum cleanup jobs, and on the state rate schedule sonic costs about 12 percent more per foot than hollow stem auger in the shallow depth band. Past 50 feet the gap grows to 20 percent or more. Those are median rates across the contractors on the schedule, and sonic is higher in every band.
But nobody pays for a well by the foot. They pay for the finished well, and there is one common petroleum job where the finished well costs less with sonic.
Why a deep petroleum well takes two days with an auger
Say a plume runs down to 40 feet and you need a well screened at 60, in clean soil below it, so you can show where the contamination stops. You drill that hole with a hollow stem auger and the auger flights carry contaminated soil down the hole with them. FDEP’s well installation procedure, SOP PCS-006, has a word for it: dragdown. You end up spreading the plume deeper while you are supposed to be measuring it.
The standard way around this is surface casing. You drill to the bottom of the contaminated zone, set a steel casing, and grout it in place. EPA guidance says to let the grout cure a minimum of 24 hours before drilling through it. Then you come back, drill through the casing, and finish the well below it.
So the well takes two days. The procedure makes it take two days.
What the second day costs
Mobilization is not the issue. On the state schedule it is charged per round trip, one charge, and it is the same whichever method you pick.
Day two costs crew per diem for the overnight stay. It costs extra vehicle trips and a second day of field staff. It also costs the casing. Surface casing is a pay item by the foot, and the statewide median across the program’s contractors is about $73 a foot. A 40 foot casing set is close to $3,000 of steel that stays in the ground when the job is done.
What sonic does differently
A sonic rig runs two drill strings at once. The core barrel goes down inside an outer casing, and the casing advances with the barrel. The hole is cased the whole way down, so contaminated soil stays behind the casing instead of riding the auger into clean ground. At the end, the casing comes back out.
FDEP’s procedure says this in plain language. Attachment B of PCS-006 lists sonic’s advantages, and one of them is “temporary override casing instead of permanent surface casing, so reduced drilling time for multiple-cased wells.” The well that takes an auger crew two days takes a sonic crew one. One published job in Alaska had a sonic rig setting 220 foot wells inside a single shift.
Sonic also makes less waste. Industry sources put the reduction in investigation-derived waste at 70 to 80 percent compared to auger drilling. Cuttings from a petroleum site go in drums and get disposed of as contaminated material, so fewer drums is a real number on the invoice, not a footnote.
When sonic wins and when it loses
Sonic wins on the well I described above: deep, screened below a plume, cased through the contaminated zone. It wins bigger on a program with several wells like that, because the saved day and the saved casing footage happen again at every location. It also wins in ground that fights an auger. Heaving sands below the water table run up inside the auger flights, and cobbles stop them outright. A stalled rig burns a day just as surely as a grout cure does.
Sonic loses on shallow wells, and it is not close. A 25 foot monitoring well with no plume to case off takes an auger crew a few hours, and the sonic rate premium buys you nothing. FDEP’s own table in PCS-006 calls sonic cost prohibitive for most shallow monitoring wells. That is fair.
Run your own numbers
That is why sonic is in the calculator. It prices hand auger, direct push, hollow stem auger, and sonic off the same FDEP rate schedule, so you can put in a real well program and look at the totals instead of arguing about the per-foot rate at a party.
The calculator is free: Florida Environmental Drilling Cost Comparison
Nicholas Moran, PG
Moran Rocks LLC, Boca Raton, Florida
FAQ
Is sonic drilling more expensive than hollow stem auger?
Per foot, yes. On the Florida DEP rate schedule, sonic runs about 12 percent higher than hollow stem auger at shallow depths and 20 percent or more at deeper intervals. Total job cost is a different question. A deep well that needs surface casing takes two days with an auger and one day with sonic, and the auger job also pays for the casing footage.
Why set surface casing in a contaminated zone?
To keep the drill from dragging contamination into clean soil and groundwater below the plume. FDEP calls this dragdown. The casing seals off the contaminated interval so the well can be completed below it.
How deep can hollow stem auger drill?
Guidance puts the practical limit around 100 feet in favorable conditions, with about 150 feet as a maximum. Depth is rarely the deciding factor on petroleum jobs in Florida. Ground conditions, like heaving sands and cobbles, and the need to case off a plume matter more.